Title:
Lack of transparency elevates Qatari construction costs
Standfirst:
UCC highlights the knock-on effect of absent details
and a lack of timeframes in Qatar’s tendering process
Copy:
Qatar could be forgiven for thinking that the fierce competition for its
projected infrastructure projects creates the ideal environment for government
bodies to dictate the terms of their tendering processes, but UrbaCon Trading
& Contracting (UCC) highlights the risk of keeping contractors in the
perpetual dark.
Submitting tender documents for large projects can involve a lot of time
and money on the part of the contractor, and a lack of provision of detailed
project specifications and timelines for the evaluation of bids serves only to
muddle an already complex process.
Mohamed Moataz
AlKhayat, CEO of UCC, notes: “Since the majority of these public projects are
design and build, the submitted proposal requires a concept design and the
hiring of an international consultant, so it costs time, money, and a lot of effort
to assemble the tender documents, perhaps over two or three months.”
Submissions
might then be followed by six months of silence, and contractors can even find
themselves discovering the results of the process in news announcing the award
of the project to another party.
Dr. Basim
Ibrahim Mohammed, deputy MD of business development at UCC, says: “Everybody,
not just me, is saying that there is poor transparency. Qatar is unique in the
Gulf region in opening the bids in secret, and there is little respect to the
contractor who contributed and submitted a bid – they do not list the bidders
or their figures; they are not obliged to accept any of the bids; and you
cannot protest.”
Further
to this many of the clients are not even transparent enough to tell the bidders
even about some of the basic details of their plans or when they are going to
announce the award or commence construction.
Since these
bids require specific CVs – for the project director, geotechnical engineer, everybody
senior – this locks these people to a specific project, and with prolonged delays
this presents a dilemma.
Dr. Mohammed adds: “On a recent submission we asked whether underground
utilities needed to relocated, and the reply was that there was no information,
but that the contractor would be responsible. However, this is very vague –
sometimes this will cost you 20-50 million, and an added 6-12 months of time.”
Ramez AlKhayat, MD of UCC, comments: “It is harming Qatar right now,
because astute contractors are applying a factor of safety when estimating bids
– the only way you can capitalise on this risk is to allow something, and this
is inflating construction rates in Qatar relative to the other countries Gulf
region.”
While the scale of projects in Qatar and the volume of the public projects
being tendered no doubt tests the government’s ability to process submissions
in a consistently timely manner, more transparent processes would ultimately allow
contractors to reduce their safety margins and of course their prices.
[[END]]
Further information about UrbaCon
Trading & Contracting
UrbaCon
Trading & Contracting is a design and construction services company based
in Doha, Qatar. Providing program and project management through to design
build and general contracting, UrbaCon is currently working on the 388,000m2
Mall of Qatar as well as the Salwa Resort Hotel.